top of page

Construction Info

ROAD CLOSURE.png

Provided below is current construction information. Please remember that construction schedules can be impacted by a variety of factors to include weather, materials or resource scheduling, or nearby events. ​ 

Current Construction Information (April 15, 2024):

Construction.png

Pima Road:

  • Pima Road traffic is currently shifted to the inside lanes (nearest the median) on either side of the road for crews to work on either side of Pima Road.

  • Crews continue work through this week at the sound wall on the west side of Pima Rd to clean-up debris or material on either side of the sound wall.

  • Work will take place this week to remove the temporary detour that was placed earlier in the project on the south side of Happy Valley Road, and restore that area.

  • Crews continue work in the channel on the east side of Pima Road to install landscaping, rip rap, and gabion baskets (wire cages filled with large rocks), and this week will begin installation of decomposed granite (DG) in the channel.

  • Scheduled to take place Monday, April 22, crews will lower utilities, such as manholes and valves, in Pima Road to prepare for upcoming milling and paving.

  • Scheduled to take place April 29 - 30, during night hours, crews will mill (remove) asphalt and crack seal at various locations along Pima Road to prepare for upcoming paving of the surface course (top layer) of asphalt on Pima Road.

  • Scheduled to begin the week of April 22, crews will install handrail along the channel, and the week of April 29 will hydroseed the channel.

  • Paving of the surface course (top layer) of asphalt for Pima Road is currently scheduled for mid-May.

Happy Valley Road:

  • Happy Valley Road traffic remains one lane in each direction with traffic on either side of the road from Pima Road to Grand Vista Road, with the Golf Club Drive roundabout operational, and traffic from 101st Place to Alma School Road on the north side of the road. Happy Valley Road traffic is shifted to the north side of the median island onto temporary asphalt through the Alma School intersection, still one lane in each direction, with left turns permitted from the thru lane.

  • Crews are scheduled to work on the north side of Happy Valley, between 101st Place and Alma School, over the next few weeks to install storm drain pipe and catch basins as part of drainage improvements.

  • Crews are scheduled to begin work this week to install median curb, outside curb, and sidewalk ramps on the south side of the future Alma School roundabout.

  • Grading crews are working to prepare the subsurface of the roadway for paving on the south side of the future Alma School roundabout, which is currently scheduled for paving of the base course (bottom layer) of asphalt on Friday, April 26.

  • Scheduled for the week of April 29, electric crews are scheduled to set streetlights at the future Alma School roundabout.

  • Scheduled for early May, Happy Valley Road traffic at Alma School will be shifted to accommodate the next phase of work at the roundabout. More information will be provided prior to that shift taking place.

During construction, business and resident access will be maintained, although there may be times wherein it will not be the most direct route, so please allow extra time for your travel during construction. Thank you for your patience during construction.

Please continue to patronize your local businesses in the project area.

bottom of page